develop schedule
Submitted by vijayavadrevu on Fri, 05/31/2013 - 10:17
Resource limitations are considered during develop schedule and are part of
A)Resource calendars
B)Critical Path method
C)Schedule network analysis
D)Resource levelling
Forums:


Vishwanath
Fri, 05/31/2013 - 10:28
Permalink
B
B
cnppmp
Fri, 05/31/2013 - 15:05
Permalink
D
D, Resource levelling.
Regards
CN Patil
vijayavadrevu
Fri, 05/31/2013 - 16:10
Permalink
I too have taken option D
I too have taken option D where as answer is given as B i.e., CPM. I would like to have explanation for option B please
Geethika
Fri, 05/31/2013 - 20:51
Permalink
Critical Chain method
Critical Chain method accounts for limited resources (pmbok 155)
But Resource leveling is more close answer in the available options
vijayavadrevu
Mon, 06/03/2013 - 06:15
Permalink
Thank You!!!
Thank You!!!