develop schedule

Resource limitations are considered during develop schedule and are part of

A)Resource calendars

B)Critical Path method

C)Schedule network analysis

D)Resource levelling

 B

cnppmp's picture

D, Resource levelling.

Regards

CN Patil

 I too have taken option D where as answer is given as B i.e., CPM. I would like to have explanation for option B please

Critical Chain method accounts for limited resources (pmbok 155)

But Resource leveling is more close answer in the available options