stakeholders formal acceptance of completed deliverables
Submitted by san on Tue, 05/21/2013 - 04:44
You have recently joined as a project manager of an equipment manufacturing company. Your project sponsor stresses the importance of obtaining stakeholders` formal acceptance of completed deliverables. This should be done:
1 At the end of the project
2 At the end of each project phase
3 After deliverables are completed and ready for review
4 After project milestones are defined
Forums:


cnppmp
Tue, 05/21/2013 - 06:19
Permalink
3
formal acceptale of eliverables is part of Verify Scope (Interim deliverables) and these are the inuts ofr for the final closure of phase or project.
Regards
CNP
sanskrit
Tue, 05/21/2013 - 12:10
Permalink
3
Verification of interim deleverables is Verify Scope
sanskrit
Tue, 05/21/2013 - 12:11
Permalink
Option 3
Verification of interim deleverables is Verify Scope , Verification of Final Product Scope Closing
vijayavadrevu
Wed, 05/22/2013 - 06:46
Permalink
It should be 3 after the
It should be 3 after the deliverables are validated by Perform Quality Process (inout to Verify Scope)
jvleminc
Mon, 05/27/2013 - 19:44
Permalink
I agree this is part of
I agree this is part of Verify Scope, but can't the answer be 2? As per Rita's book, on page 164 it states that "Verify scope can be done at the end of each project phase". Moreover, in answer 3, why would the deliverables be reviewed AFTER their formal acceptance by the stakeholder?
What do you think?