What should be done first!!

Hello Experts,

Just wanted to clarify a small doubt.

If a stakeholder request for a change to modify the scope slightly to add a feature. Project is in execution phase. What should be te response of the PM ?

Choices:

Analyze the impact of the request on the other factors? OR

Document the change request as per project scope management plan and then do a analysis.

On a side note : I have seen questions where analyze the impact is been choosen as a first choice.

My ask is : What is PMI theory on this.?

 

Regards,

Ritesh

admin's picture

You should first document the CR before analyzing the same.

Made a note of this. Thanks Much PMZilla!!

 

Another small boubt :

 

Q:Lessons learned created by which of the following (a questions from exam central)

Choices :

Stakeholder

Project team

Opted stakeholder however the right choice was given as project team..

Earlier mock i attempted, stakeholder was selected as a right choice. Not sure what to select in case the same question appears in the PMP actual exam. :)

Pl suggest.

Regards,

Ritesh

 

 

Made a note of this. Thanks Much PMZilla!!

 

Another small boubt :

 

Q:Lessons learned created by which of the following (a questions from exam central)

Choices :

Stakeholder

Project team

Opted stakeholder however the right choice was given as project team..

Earlier mock i attempted, stakeholder was selected as a right choice. Not sure what to select in case the same question appears in the PMP actual exam. :)

Pl suggest.

Regards,

Ritesh