What should be done first!!
Submitted by rit_mis on Wed, 11/21/2012 - 01:00
Hello Experts,
Just wanted to clarify a small doubt.
If a stakeholder request for a change to modify the scope slightly to add a feature. Project is in execution phase. What should be te response of the PM ?
Choices:
Analyze the impact of the request on the other factors? OR
Document the change request as per project scope management plan and then do a analysis.
On a side note : I have seen questions where analyze the impact is been choosen as a first choice.
My ask is : What is PMI theory on this.?
Regards,
Ritesh


admin
Wed, 11/21/2012 - 02:06
Permalink
You should first document the
You should first document the CR before analyzing the same.
rit_mis
Wed, 11/21/2012 - 12:42
Permalink
Made a note of this. Thanks
Made a note of this. Thanks Much PMZilla!!
Another small boubt :
Q:Lessons learned created by which of the following (a questions from exam central)
Choices :
Stakeholder
Project team
Opted stakeholder however the right choice was given as project team..
Earlier mock i attempted, stakeholder was selected as a right choice. Not sure what to select in case the same question appears in the PMP actual exam. :)
Pl suggest.
Regards,
Ritesh
rit_mis
Wed, 11/21/2012 - 12:42
Permalink
Made a note of this. Thanks
Made a note of this. Thanks Much PMZilla!!
Another small boubt :
Q:Lessons learned created by which of the following (a questions from exam central)
Choices :
Stakeholder
Project team
Opted stakeholder however the right choice was given as project team..
Earlier mock i attempted, stakeholder was selected as a right choice. Not sure what to select in case the same question appears in the PMP actual exam. :)
Pl suggest.
Regards,
Ritesh