I have two questions.
1) definitive estimate - Is it =-10 to +15%(as per PMBOK) ot -5 to +10% (as per Rita)
2) When you close the project what is the last thing you do?
Rita has release resources, but the mock tests I am taking on pmstudy etc says that you lessons learned as last? which is true?