Doubt in Develop Schedule Question

Hi Team,

Got doubt in following question from Rita's:

A new product development project has four levels in the WBS and has been sequenced using the precedence diagramming method. The activity duration estimates have been received. What should be done NEXT?

a) Create an activity list.

b) Begin the WBS.

c) Finalize the schedule.

d) Compress the schedule.