PMBOK Procurement Confusion
Submitted by vejandla on Fri, 07/30/2010 - 19:16
Forums:
On page 317, the last line on first para says...
"the processes from Plan Procurement through Close Procurements are performed for each item to be acquired"
this sounds like if I have to procure multiple items/services for the project, then I need to have different Procurement Management Plan for each of those items/service
On page 326, the last line on first para says...
"However, multiple products or sevices can be grouped as one procurement item within a single SOW"