TCPI
Submitted by sai_murthy on Sat, 07/31/2010 - 03:46
Forums:
Question: Calculate the to-complete performance index of your project, based on EAC, when the actual cost of your project is $200,000, cost variance of your project is $25,000 and the budget at completion of your project is $350,000.