rita question 235

All are outputs of MOCO project work except.


a) rejected change req


b) recommended corrective actions


c) forecasts


d) recommended defect repair.


Answer is A.  Given explanation -> rejected changes are an output of integrated change control.


We know that perform integrated change control is a MOCO activity right ? What am I missing here ?


question id 235 from fast track.