rita question 235

All are outputs of MOCO project work except.


a) rejected change req


b) recommended corrective actions


c) forecasts


d) recommended defect repair.


Answer is A.  Given explanation -> rejected changes are an output of integrated change control.


We know that perform integrated change control is a MOCO activity right ? What am I missing here ?


question id 235 from fast track.

admin's picture

There is MOCO process group and MOCO project work ( which is process )  Refer page 61 of PMBoK.

So Rejected change requests are not part of MOCO project work since its part of Integrated Ch. control.

Hope this clarifies.

Thanks for the clarification. I misread the question as MOCO process group instead of MOCO project work.


Time to get over with this.