All are outputs of MOCO project work except.
a) rejected change req
b) recommended corrective actions
c) forecasts
d) recommended defect repair.
Answer is A. Given explanation -> rejected changes are an output of integrated change control.
We know that perform integrated change control is a MOCO activity right ? What am I missing here ?
question id 235 from fast track.
Forums:


admin
Thu, 07/28/2011 - 01:44
Permalink
There is MOCO process group
There is MOCO process group and MOCO project work ( which is process ) Refer page 61 of PMBoK.
So Rejected change requests are not part of MOCO project work since its part of Integrated Ch. control.
Hope this clarifies.
nbk
Thu, 07/28/2011 - 03:25
Permalink
Thanks for the clarification.
Thanks for the clarification. I misread the question as MOCO process group instead of MOCO project work.
Time to get over with this.