Manage and COntrol PW leads to PM plan update
Submitted by Freddo on Fri, 08/26/2011 - 09:57
Forums:
Hi guys,
Passing the test in 3 days ...
In the PmBok, page 90, we can see that 4.4. Monitor and Control Project Work leads to
a) 4.2. Develop Project managament plan
b) 4.5 Perform integrated Change Control
My concern is about a) => how could we directely update the PM Plan withoud an approved change request.