Which method for CPM Start Date 0, or 1.
Submitted by brian mahon on Fri, 11/13/2015 - 16:48
Forums:
The PMBOK SAYS 1 as do most other sources, but Rita uses 0. I'm assuming the accepter method is to use 1 as the start date as that's the ref in the PMBOK.
So can we just learn the start = 1 approach for exam purposes or do we need to be aware of the zero calc also?
Thanks in advance