SPI question
Submitted by sampathgowri on Sat, 04/14/2012 - 23:41
Forums:
This was a question from certchamp.
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, but the actual work completed is 20% of the total work. What is Schedule Performance Index (SPI) in this case?
A)1.66
B)1
C)2.5
D)1.9
Can somebody explain how A is the right answer.
Thanks.