***Critical Path - Question***
Submitted by sam_jain on Tue, 04/17/2012 - 23:41
Forums:
You are the project manager for Software Development project. The feasibility study can start any time and takes 1 week and Requirement gathering takes 2 weeks which can start only after feasibility study.