is this q is clear
Submitted by sspawar on Sun, 04/29/2012 - 17:35
Forums:
You are a project manager for one of many projects in a large and important program. At a high-level status meeting, you note that another project manager has reported her project on schedule. Looking back on your project over the last few weeks, you remember many deliverables from the other project that arrived late. What should you do? a) Meet with the program manager