which one is right?
Submitted by kumark on Sat, 11/10/2012 - 08:13
Forums:
Q- The project is being completed faster than time planed. Which of the following would NOT account for why this has occurred? A- Trend analysis was used to estimate the need for some testing B- A pre-made item was purchased versus creating one by the team C- A critical path and a non-critical path activity were fast tracked D- A critical path activity was compressed