Q- The project is being completed faster than time planed. Which of the following


would NOT account for why this has occurred?


A- Trend analysis was used to estimate the need for some testing


B- A pre-made item was purchased versus creating one by the team


C- A critical path and a non-critical path activity were fast tracked


D- A critical path activity was compressed


I would say Option A because B/C/D could be one of the reasons for completing the project earlier but "A" would not lead to any reason for completing is faster

i thought the same but it is option C and explanation given as you are fastracking CP and a non CP actvitys together and there will be float on non CP activity which will not a/c for early finish.  I think this make sense.


Thanks