As a project manager, you have assessed that your project team is engrossed too much in reviewing potential changes to a project that they do not have time to complete the actual project work as per the overall project plan. Which of the following is most likely reason for this problem?

1. No change control board

2. Due diligence not done to identify stakeholders

3. A poor communication management plan

4. An unclear project charter