Confused - calculate EAC and VAC
Submitted by pmpSGI on Tue, 06/28/2011 - 19:56
Forums:
Information provided -
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=15.
Situation 1. The type of variances that have occured are believed to be atypical, and these variances are expected to continue.
Situation 2. The variances are typical and do not expect these variances to continue.
Calculate VAC for the project in both situations.