please help answer this TRICKY question from i2m Management Services
Submitted by PMPBOY on Thu, 07/07/2011 - 01:12
Forums:
Question: approved change requests and approved corrective actions are an output of which of the following processes:
A. Performance Control
B. Quality Control
C. Manage Stakeholders
D. Risk Monitoring and Control
I selected 'D' but they said that the correct answer is 'C'.
PMP Experts please clarify how correct answer should be C.