Q on Integrated Change request
Submitted by arindammaiti on Tue, 09/27/2011 - 23:07
Forums:
Which one is the correct sequence for implementing changes
a. Identify Change, Look for impact and then ask for formal change request
or
b. Identify Change, ask for formal change request and then look for impact
?
