Q on Integrated Change request

Which one is the correct sequence for implementing changes

a. Identify Change, Look for impact and then ask for formal change request

or

b. Identify Change, ask for formal change request and then look for impact

?

It should be Option a.


Rita's PMP Exam prep also explains these steps in detail.