Control Chart question

Can you please let me know the answer for this question:

Question 43: You are producing aluminum dowels. The control limits of this
production process are 14.9cm and 15.1cm. The specification limits are 14.8cm and
15.2cm. Inspection shows that the last 5 dowels produced are 15.2cm long. What do
you do?
A.) Deliver them to the customer.
B.) Don’t’ deliver them to the customer.
C.) The process is out of control and needs to be adjusted.
D.) You should not be inspecting because you have clear control and specification
limits.