which contract type ?
Submitted by pmasp1 on Wed, 11/30/2011 - 22:48
Forums:
A project manager is in trouble because he took on a contract that overran its budget, and now he has to eat
the cost out of his own budget. Which of the following BEST describes his contract?
A. Time and materials
B. Fixed price
C. Cost plus incentive fee
D. Cost plus percentage of cost