Why??? for this answer
Submitted by vikasmisra on Sun, 04/08/2012 - 06:34
Forums:
Post mortem earned value analysis of a project showed the following data: SPI: 0.78 CPI: 1.00 What is this telling you?
The correct answer (as per the book) is
o The project has been terminated before completion. At that time it was behind schedule and on budget
How do we know if the project was terminated and not completed??