Why??? for this answer
Submitted by vikasmisra on Sun, 04/08/2012 - 06:34
Post mortem earned value analysis of a project showed the following data: SPI: 0.78 CPI: 1.00 What is this telling you?
The correct answer (as per the book) is
o The project has been terminated before completion. At that time it was behind schedule and on budget
How do we know if the project was terminated and not completed??
Forums:


pmp_man
Sun, 04/08/2012 - 06:39
Permalink
This is typical PMP question
Post mortem ALWAYS means the project is terminated. ->>>> That Simple
This is typical PMP type question.
vikasmisra
Sun, 04/08/2012 - 06:49
Permalink
Thanks Man. I somehow missed
Thanks Man. I somehow missed this concept and I saw this question coming up few times at different places.
krantikumar50
Sun, 04/08/2012 - 10:57
Permalink
Thanks...
Thanks PMP_MAN. No doubt, its so simple, but many, like me, would have never thought of this. Thank You so much for clarifying. I would always wonder how does one derive that the project was terminated early. Now, I know that since the question mentioned post-mortem, so here we are. Thanks much, KK....
projmanpro
Sun, 04/08/2012 - 22:23
Permalink
This is the exact analysis
This is the exact analysis and complete explanation :
postmortem means "after death" which in the project imply "termination". Showing the SPI = 0.78 which is <1 (meaning behind schedule) and the CPI = 1 (meaning on budget).
Thus, the correct answer is - the project has been terminated before completion at the time it was behind schedule (SPI<1) and on budget (CPI=1).
Vikas, you have to consider well and detailed explanations to questions if you are looking for a good PMP exam sample questions.