Project terminated vs Closed
Submitted by sbumich on Wed, 04/25/2012 - 20:57
Forums:
PMP experts, how do you know if project was terminated early or finished successfully?
Lehmann's Q:
92. Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that? 92 |