Hi everybody,

I need clarification for the following two questions and their explanations from Rita 6th :

P496 Q14

Rita Answer is C. I don't think so as it's impossible to provide an accurate estiamte of the actual costs with unclear project scope (see the underscored words in question above) at that time. I chose B. What's your opinion? Please elaborate your choice and reasons if possible.

P497 Q19

Rita described a situationas below: