Change Control 3 sample senarios
Submitted by joe_aad on Wed, 05/09/2012 - 22:46
Forums:
Assuming the following senarios,
1- The project is already delayed or over buget, and you dont seem to find a way to solve what do you do, do you create a change request to get a new schedule and cost baseline?
2- Some project activities are delayed you know you can make up if you switch resources around, do you create a CR or go to ICC?