Question 108 from Oliver Lehmann 175Qs
Submitted by danny2012 on Thu, 06/07/2012 - 08:31
Forums:
108. Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000, EV: $1,000,000, AC: $1,200,000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC – EV) is at $1,000,000, what should be your new EAC (estimate at completion)?
o $1,800,000
o $2,000,000
o $2,200,000
o $2,400,000