a Code of Ethics question
Submitted by danny2012 on Sat, 06/09/2012 - 13:58
Forums:
You are doing a project under cost-reimbursable contract where the target price was $ 1,200,000. Your project is nearing completion and CPI is currently 1.3. You are concerned that you will be losing money by billing for less. In this context, you should: