PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

EVM

One of your project has BAC= 270000.. In a point of time AC measured 100000. while CPI was 0.90. What will be the EAC of your project if later part CPI is measured 1.06.



  1. 260000

  2. 270000

  3. 300000

  4. None of above