I am not convinced could you explain:
Q.
What would resource leveling usually result in?
A. Decrease in project duration
B. Fast tracking
C. Crashing
D. Increase in project duration
Answer:
D
Explanation
Planning -Time Management Resource leveling is applied to allocate scarce resources to critical path activities first, but this often results in a project duration that is longer than the original schedule estimates.
-------------------------------------------