PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

I am not convinced could you explain:

Q.

What would resource leveling usually result in?
 

A. Decrease in project duration

B. Fast tracking

C. Crashing

D. Increase in project duration

Answer:

D

Explanation

Planning -Time Management Resource leveling is applied to allocate scarce resources to critical path activities first, but this often results in a project duration that is longer than the original schedule estimates.

-------------------------------------------

It is a Q from a well reliable and so far most helping website of PMP.