You have finished estimating costs for your project. What is your next activity to manage the costs?

A.) Develop Cost Performance Baseline
B.) Develop Work Performance Measurements
C.) Develop Budget Forecasts
D.) Plan Quality

------------------------------
Hint: Determine Budget is the immediate process after the Estimate Costs process.
------------------------------