Free PMP Exam Sample Question
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
You have finished estimating costs for your project. What is your next activity to manage the costs?
A.) Develop Cost Performance Baseline
B.) Develop Work Performance Measurements
C.) Develop Budget Forecasts
D.) Plan Quality
------------------------------
Hint: Determine Budget is the immediate process after the Estimate Costs process.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
Please click here for the correct answer and explanation.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-management-prepcast.com


amber
Mon, 10/22/2012 - 12:42
Permalink
Answer is A
The correct answer is A