PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Verify Scope Question

 A project manager receives a deliverable from one of the team members to provide to the customer. While looking at the deliverable, the project manager notes that the document is smaller than what he expected and does not contain what he thought it should. The project manager should FIRST:

A. Discuss it with team member

B. Contact the team members' manager to get the person additional training

C. Audit the development process

D. Complete the verify scope process.

Please justify your answer. 

Thanks,

Riyaz

Pages