Verify Scope Question
Submitted by riyaz145 on Wed, 12/05/2012 - 14:39
A project manager receives a deliverable from one of the team members to provide to the customer. While looking at the deliverable, the project manager notes that the document is smaller than what he expected and does not contain what he thought it should. The project manager should FIRST:
A. Discuss it with team member
B. Contact the team members' manager to get the person additional training
C. Audit the development process
D. Complete the verify scope process.
Please justify your answer.
Thanks,
Riyaz
Forums:
sspawar
Thu, 12/06/2012 - 01:12
Permalink
A
In any case discussion with T M will be the 1st action.
aarush78
Thu, 12/06/2012 - 03:56
Permalink
SS pawar has given the right
SS pawar has given the right answer ...first inputs from the team members is required to know the complete situation and then PM would initiate any corrective action if required
riyaz145
Thu, 12/06/2012 - 04:24
Permalink
Even I thought the same, but
Even I thought the same, but the answer given was D.
Obtained from PMfasttrack question bank
mpavas
Sun, 12/09/2012 - 16:52
Permalink
The ansswer should be A.
The ansswer should be A.
aarush78
Mon, 12/10/2012 - 03:21
Permalink
can you check with rita's
Riyaz,
can you check with rita's team they will surely answer the detailed explanation as to why they gave that answer ..i think their email id is given in Rita's book
sspawar
Wed, 12/12/2012 - 11:47
Permalink
what is that q ID
Dear RIYAZ
can you write here that q ID number
what is REETA's explanation.
sspawar
Fri, 12/14/2012 - 10:36
Permalink
RITA Q ID 330
RITA Q ID 330
The correct answer is D.
Such a review compares the deliverable to the requirements. The project manager might have misunderstood and it would be best to check before talking to the team member.
Source: PMP® Exam Prep
Page: 167
----------
above is Rita's explanation, but in my view, for verifying the deliverables he or she must have to discuss to team member , He or She cant verfy himself or herself withot consulting the report and concerned person.
Connect2pmzilla
Fri, 12/21/2012 - 23:58
Permalink
D is correct
Answer D is correct. Porject manager can verify the scope the deliverables by doing that review before even reach the team member. If he misunderstood, he does not need to verify with Team member.
if his understanding is wrong and If he directly verifies with team member, it might demotivate the team member eventhough he did it correct.