whats wrong with this EVM status?
Submitted by Prakash999 on Wed, 12/19/2012 - 03:38
Forums:
The metrics for one project show a BAC of $1100, an EV of $998, and a EAC of $1099. However the project manager is reporting an ETC of $354 in her presentation.
Can someone confirm if this calculation is good to assess this situation?
Since the project is so close to completion, ( about 91% of work is completed - based on EV )
Hence, EAC = (BAC/CPI) = (BAC*AC)/EV ; Using these ; AC is slightly lesser than but very close to 998;