Need help on Q.
Submitted by peeyushm on Mon, 01/28/2013 - 09:47
Forums:
What would be the answers of following Q?
1) Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total float. As of today, task one andtwo have been completed on schedule. How many days of float remain in the schedule of these tasks?