EVM question
Submitted by raza82 on Tue, 01/29/2013 - 16:52
Forums:
A project manager reported the following earned value data: PV: $12,400,000 EV: $14,500,000 AC: $14,500,000 What does this mean?
a The project is over budget and on schedule.
b The project is under budget and on schedule
c The project is on budget, but behind schedule.
d The project is on budget and ahead of schedule.
My answer is a.