EVM question
Submitted by raza82 on Tue, 01/29/2013 - 16:52
A project manager reported the following earned value data: PV: $12,400,000 EV: $14,500,000 AC: $14,500,000 What does this mean?
a The project is over budget and on schedule.
b The project is under budget and on schedule
c The project is on budget, but behind schedule.
d The project is on budget and ahead of schedule.
My answer is a.
Forums:


sunitaPMP
Tue, 01/29/2013 - 20:56
Permalink
ans is D) The project is on
ans is D) The project is on budget and ahead of schedule..
SV=EV-PV=14,500,000-12,400,000=2100,000
CV=EV-AC=14,500,000-14,500,000=0
So its on budget and ahead schedule.
raza82
Wed, 01/30/2013 - 05:22
Permalink
got it
yes ur right, u know sometimes when ur so tired of giving mock test, we tend to forget the basics.
Thats what happened to me last night when I was giving Oliver Lehman's test :-)
And I couldn't just understand how the answer was D
steelproject2012
Sun, 02/03/2013 - 13:11
Permalink
Alternatively, we can say:CPI
Alternatively, we can say:
CPI = EV/AC = 14.5/14.5 = 1.00
SPI = EV/PV = 14.5/12.4 = 1.17
In sum, the project is on budget (CPI=1.0) and ahead of schedule by 17% (SPI=1.17)