Time: PDM calculate logical relationships
Submitted by daso on Fri, 02/08/2013 - 16:18
Forums:
| Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B? |