Time: PDM calculate logical relationships
Submitted by daso on Fri, 02/08/2013 - 16:18
| Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B? |
||
| 36 days | ||
| 37 days | ||
| 39 days | ||
| 42 days | ||
I thought it is 36, but that's wrong. How do you calculate that?
Forums:



sspawar
Sat, 02/09/2013 - 01:51
Permalink
20 (Act1) + 10-2(Act3) +
20 (Act1) + 10-2(Act3) + 3+6(Act4) = 37
Act 2 will be not added as activity 3 is finishing before 2 days of it and act 4 is starting on finishing of 3.
steelproject2012
Sat, 02/09/2013 - 01:26
Permalink
Can someone pls explain the
Can someone pls explain the relationship from Act2 - Act4:
from Act2 -> Act3 = FF-2 means 30-2 = 28, right?
(i) What will cause Act2 to finish on the 28th day when actually Act2 takes 10 days = 30th day?
(ii) What will be the maximum total duration btw Milestones A and B under same situation?
Thanks