Questions with confusing answers
Submitted by Reeta on Tue, 03/05/2013 - 14:27
Forums:
Pls help me understanding the answer ?????
1. You are managing an infrastructure project which is nearing completion when a
major stakeholder points out a flaw in the design which could make the entire structure
weak. He suggests you construct two support pillars which would provide the necessary
support. You are worried that this change could impact the schedule and cost of the