Few questions from mock up - clarification needed
Submitted by Jgrind07 on Mon, 03/18/2013 - 04:26
Forums:
Friends,
I was taking a lite mock up test from Christopher Scordo and came accorss the following questions.
1. What does a Cost Performance Index (CPI) of 1.0 indicate?
A.The project is over budget.
B.The project is right on budget.
C.The project is under budget.
D.The project is ahead of schedule
I slected B as the answer. But author says its D.