Fast Track your schedule
You are required to "fast-track" your project schedule. THerefore you should be prepare to:
a) Eliminate some items of scope, with approporate stakeholder approval
b) Increase resources if they become over-allocated
c) Communicate a time extentsion
d) Shorten the duration fo critical path activities
Source of question: Ferndale's pmp
Given answer is b. I understan first part "increase resource" but don't understand second part "if they become over-allocated"
Won't "d" be possible answer?