You are required to "fast-track" your project schedule. THerefore you should be prepare to:


a) Eliminate some items of scope, with approporate stakeholder approval


b) Increase resources if they become over-allocated


c) Communicate a time extentsion


d) Shorten the duration fo critical path activities


Source of question: Ferndale's pmp


Given answer is b. I understan first part "increase resource" but don't understand second part "if they become over-allocated"


Won't "d" be possible answer?