A Risk Question
Submitted by Jgrind07 on Sun, 04/28/2013 - 03:10
I have been doing a mock test in a mobile PMP application and came across this question.
A risk is not realized during the intended timeframe. What should the project manager do next?
A. Upadte the risk responce plan
B. Update the WBS
C. Update the project schedule
D. Identify secondart risk.
What is your choice and explain your rational behind your choice?
Thanks
Jai
Forums:
sspawar
Sun, 04/28/2013 - 03:20
Permalink
A
A
Jgrind07
Sun, 04/28/2013 - 03:22
Permalink
Thanks for Pawar. You
Thanks for Pawar. You explaination please?
sspawar
Sun, 04/28/2013 - 03:24
Permalink
AIn monitor and control
A
In monitor and control process risks are - reassessed, audited and reviewed accordingly risk register is updated by updating risk response plan.
updating of wbs /schedule/cost includes this action
Jgrind07
Sun, 04/28/2013 - 03:29
Permalink
Got it, thanks again Pawar.
Got it, thanks again Pawar.