A Risk Question

I have been doing a mock test in a mobile PMP application and came across this question.

 

A risk is not realized during the intended timeframe. What should the project manager do next?

A. Upadte the risk responce plan

B. Update the WBS

C. Update the project schedule

D. Identify secondart risk.

What is your choice and explain your rational behind your choice?

Thanks

Jai

 A

Thanks for Pawar. You explaination please?

  A

In monitor and control process risks  are - reassessed, audited and reviewed accordingly risk register is updated by updating risk response plan.

updating of wbs /schedule/cost  includes this action

Got it, thanks again Pawar.