Question:Regarding Shortening Critical Path
Submitted by Aishwaryanand on Tue, 12/31/2013 - 02:06
I came across the question that if you have to crash one of many activities on the critical path which one you choose larger duration or smaller duration (no foinacial data provided) and why.


admin
Wed, 01/01/2014 - 04:37
Permalink
If you crash a larger
If you crash a larger duration activity it may be less effort. A task taking 100 hours may be easy to crash, you can add a resource and expect it to complete early.
For smaller tasks say 10 hours, adding resource may not provide as much benefit as there will be some rampup time required to get the resource.
Also by Pareto rule, you should always separate critical few from Trivial Many. Crashing one large task may be more practical then focussing on crashing several small tasks as it will consume more management bandwidth.
Having said all this, it really depends on the scenario.
Aishwaryanand
Thu, 01/02/2014 - 00:14
Permalink
Thanks
Thanks Admin
That is what I wanted to clarify.Excellent explanation.
Thanks again for quick reply.
Regards
Anand